By Overseas of business Department of Hubei DIJIAN Construction Co.,ltd undertake the construction of overseas in Mongolia MAK1500T / cement project engineering survey field work on August 31, 2010 were all over. The project construction process strictly according to Chinese norms, standards, organization implemented since July 19, 2010,including a total of 6 sets of drilling machine which complete drilling of 80 (controlled drilling 30; others drilling 50), total dept was1,047 meters.Investigation company as a technical advisory which guide the whole field exploration work, responsible for field geological record and report writing; Mongolia and Japan participated the construction team.
Field construction site in
Hubei DIJIAN Construction Co.,ltd technical personnel and drilling workers took group photo in
Hubei DIJIAN Construction technical personnel on-site record
Japan's drilling personnel on-site construction